6 Setup
6.1 Setup steps
After
mounting and electrical connection, VEGABAR 17 is ready for
operation.
VEGABAR 17 delivers a current of 4 20 mA corresponding to the
actual process pressure.
Further settings are not necessary.
6.2 Recalibration
With both instruments with thread ring or eld housing, zero and span
can be adjusted via integrated potentiometers. Adjustment range:
l Zero ± 5 %
l Span ± 5 %
This allows, for example, the consideration of an installation position
dierent from the reference installation position.
A shifting of ze ro shifts span also respectively.
Note:
The potenti
ometer for span should only be used if you have adequate
calibration equipment (at least 3 times more precise than the deviation
of VEGABAR 17).
Recommended recalibration cycle: 1 year.
Proceed as follows:
1 Loosen the plug connector and screw the screwed ring in
connected status
2 Place the plug connector onto the instrument place and pull both
carefully out of the instrument
Instrum
ents with plug
connector or
cable out-
let
18 VEGABAR 17
6 Setup
27636-EN-120531
Seitenansicht 17
1 2 ... 13 14 15 16 17 18 19 20 21 22 23 ... 35 36

Kommentare zu diesen Handbüchern

Keine Kommentare